Maintenance changes the plantso the protection must be proved for the state the work leaves behind

Two routine maintenance jobs, one on a Welsh railway and one in a London data centre, left assets in a state their protection did not check for.

BY KINGKOF OPOKU-OHEMENG4 MIN READMON. 2 NOVEMBER 2026
Two routine jobs, and in each one a configuration the protection was never asked to check.KPL GRAPHIC · DATA: RAIB AND GOOGLE CLOUD INCIDENT REPORTS
THE STRATEGIC SIGNAL

A maintenance state is an operating configuration, and the protection has to be proved for it before the work starts and again when the asset returns. Protective logic should read the plant as it really is, because it will otherwise trust the state the drawings show.

610 m
the distance a train's ETCS equipment still showed at the end of its movement authority near Welshpool
1 feed
the London site was running on while feed B was locked out for repairs after a generator load test
6 h 8 min
the impact window of the London outage in Google's final Incident Report
15 Nov
Google's estimate for validating the generator controls at sites with similar layouts
01/ 06
01 / 06THE DEVELOPMENT

Two routine jobs, two blind spots

VAt about 23:52 on 15 September 2026 an infrastructure monitoring train running under ETCS Level 2 came to a stand near Welshpool, Powys, at the block marker that ends its movement authority. Its on-board equipment was still telling the driver there were 610 metres to go. RAIB says a component of that equipment had stopped the correct wheel diameter being stored after routine maintenance, and neither the independent speed measurement nor the trackside balises corrected the distance1.

VRAIB found weaknesses in the on-board protection arrangements, chose not to run a full investigation, and wrote to Network Rail, copied to the Office of Rail and Road and the train's operator1.

VIn London, Google's final Incident Report of 27 October 2026 explains the outage of zone europe-west2-b. A generator load test on 14 October found problems, so engineers opened and locked out the breaker on utility feed B and ran the site on one feed. When feed A failed at 06:53 BST on 20 October, the generators were never told to start, the batteries ran out at 07:00 and the zone lost power for an impact window of 6 hours 8 minutes2.

02/ 06
02 / 06WHY IT MATTERS

The protection trusted the normal state

VGoogle says the undervoltage sensing for the generator controls was wired upstream of the isolated feed B breaker. The sensors saw voltage on a path that was disconnected, and the logic, which did not check breaker position, concluded a healthy supply was available2.

AEach system was protected well enough for the configuration it normally runs in. Each job created a different configuration, a stored parameter in one case and an open breaker in the other, and the protection went on reading signals that were only true for the normal state.

FIGURE 01 · THE STATE THE WORK LEAVES
THE NORMAL STATEProtection designed and proved for the usual configuration
THE WORKIsolation, adjustment or a stored value changes the plant
THE PROOFA record that the protection sees the plant as the work left it
AProtection proved for the normal state says nothing about the state maintenance leaves.
03/ 06
03 / 06STRATEGIC IMPLICATIONS

A maintenance state is an operating state

AIsolations, lockouts, temporary feeds and changed parameters are configurations the asset genuinely runs in, sometimes for days. They belong in the safety case as states with their own proof, and on the risk register with an owner and an end date.

AIndependent checks can share the blind spot. At Welshpool two separate means of correcting the distance existed and neither did. Return to service should confirm the values and positions the protection relies on, rather than infer them from the work order being closed.

VGoogle's own response points the same way: it is freezing planned maintenance at sites with similar layouts, adding elevated approvals for configuration changes outside standard designs, and validating the generator controls at those sites, with an estimate of 15 November2.

04/ 06
04 / 06OUR PERSPECTIVE

Ask the protection what it can see

AKIS PLUS LTD's view is that every maintenance plan should carry a protection check for two moments: the configuration the work creates, and the asset's return. The question is simple to put to any team: with this breaker open or this value changed, what will the protection read, and what will it do? Asset management systems already treat change as a risk to be assessed; routine maintenance is the change that happens most often.

INetwork Rail may find a specific cause in the component at Welshpool, and RAIB's earlier report on the same line suggests support systems deserve close attention1. This article draws no conclusion on the component itself.

OUR PERSPECTIVE

The work changes the plant, and the protection has to be told.

05/ 06
05 / 06QUESTIONS FOR THE BOARD

Three questions to ask this week

  1. For our most common isolations and adjustments, has anyone shown what the protection reads and does in that configuration?
  2. On return to service, who confirms the stored values and positions our protection depends on, and where is the record?
  3. Which of our independent checks would miss the same wrong value, and how would we know?
06/ 06
06 / 06WHAT TO WATCH

The next proof points

MilestoneWho decidesStatus
Network Rail's response to RAIB on the on-board ETCS protection arrangements1Network Rail, Office of Rail and RoadLetter sent; no findings published on 2 November 2026
Validation of generator controls at sites with similar layouts2Google CloudEstimated 15 November 2026 in the report
Full generator transfer tests with both London feeds restored2Google CloudEstimated 31 October 2026 in the report; completion not yet confirmed
BOTTOM LINE

Every maintenance job should end with proof that the protection sees the plant as the work left it.

Near Welshpool a stored wheel diameter, and in London an isolated breaker, left protection trusting a state that no longer existed. Owners should treat the maintenance state as an operating configuration and prove it before work starts and when the asset returns.

EVIDENCE BOUNDARY

VVerified

  • The Welshpool event of 15 September 2026: ETCS Level 2, the train at the block marker with 610 metres still shown, the wheel diameter not stored after routine maintenance, the speed measurement and balises not correcting it, RAIB's decision and its letter, as RAIB's notice states
  • The London sequence: the generator load test of 14 October 2026, feed B locked out, single-feed running, feed A failing at 22:53 US/Pacific (06:53 BST), sensing wired upstream of the isolated breaker, batteries exhausted at 07:00 BST, the 6 hours 8 minutes impact window, as Google's final Incident Report states
  • Google's actions: the maintenance freeze, elevated approvals and control validation at similar sites with its 15 November and 31 October estimates

RReported

Nothing in this category.

AKPL analysis

  • Both protections were proved for the normal configuration and read signals true only for it
  • A maintenance state as an operating configuration needing its own proof, owner and end date
  • Independent checks sharing a blind spot, and return to service confirming values rather than inferring them
  • The two-moment protection check and the questions for the board

IInference

  • That support systems deserve close attention at Welshpool, which depends on Network Rail's findings, not yet published
SOURCES AND EVIDENCE
01Rail Accident Investigation BranchWrong side failure near WelshpoolPrimary21 October 2026

Every source above is cited in the text by its number. Paragraphs marked A or I are KIS PLUS LTD analysis or inference.