A backup countsfrom the day it was last proved end to end

A London cloud zone had batteries, generators and two controllers to start them, and on 20 October 2026 the controllers did not start the generators.

BY KINGKOF OPOKU-OHEMENG4 MIN READMON. 26 OCTOBER 2026
Two sites, two protective chains, and in each one step that did not happen when it was called.KPL GRAPHIC · DATA: GOOGLE CLOUD INCIDENT REPORTS
THE STRATEGIC SIGNAL

Redundancy is a claim until the whole protective chain has been made to work, under load, with a record of the test. Two controllers that fail the same way give a board one asset where the drawings show two.

2 of 2
the primary and backup automation controllers in London both failed to start the generators
6 h 10 min
the length of the London incident on 20 October 2026, from 07:00 to 13:10 BST
44°C
data hall temperature in the Netherlands on 15 July 2026, with the second cooling source out for construction
14 h 55 min
the length of the July incident in Google's final report
01/ 06
01 / 06THE DEVELOPMENT

Two controllers, one failure

VAt 07:00 BST on 20 October 2026 the facility hosting Google Cloud zone europe-west2-b in London lost power. The UPS battery banks took the load. Google's Preliminary Incident Report, posted on 22 October, says the automation system that starts the generators, both primary and backup controllers, failed to start them. When the batteries ran out, servers, network and storage in the zone went offline1.

VThe harm spread beyond the zone. Google says customers in the two unaffected London zones also saw errors, because of sudden demand on the remaining capacity and control-plane checks that depended on the zone that was down. The incident ran for 6 hours 10 minutes, and a final report with preventative actions is still to come1.

RCustomers of Revolut, Lloyds, HSBC and Bank of Scotland, and users of Royal Mail, DPD and Rightmove, were reported disrupted. The FCA said it was engaging with Google and affected firms, and the Treasury Committee wrote to the Bank of England and the FCA3.

02/ 06
02 / 06WHY IT MATTERS

The same shape, three months earlier

VOn 15 July 2026 a 3 ms voltage drop hit both utility feeds of zone europe-west4-a in the Netherlands. Google's final report says the side A backup power unit failed to take the load, one row of racks tripped, the chiller controller went offline so the pumps did not restart, and the redundant cooling source was unavailable because of known construction work. The data hall reached 44°C and the incident lasted 14 hours 55 minutes2.

AEach site had redundancy on its drawings. In each, one step in the chain did not happen when it was called: a controller, a backup unit, a pump restart, a cooling source taken out for works. A chain is as available as its least proved link.

FIGURE 01 · THE PROTECTIVE CHAIN
THE DRAWINGBatteries, generators, two controllers, a second cooling source
THE CALLGrid fault: every link must act, in order, under load
THE PROOFA dated record that the whole chain last worked end to end
ARedundancy on a drawing becomes a fact only when the whole chain has been made to work.
03/ 06
03 / 06STRATEGIC IMPLICATIONS

Duplicated controls can share one failure

AA primary and a backup controller that fail together behave as one asset. Duplication protects against a single component failing; it gives no protection against a shared design, shared logic or a shared trigger. The asset register should show which protective layers are truly independent and which only look it.

APlanned works change the design in force. A cooling source taken out for construction is a temporary loss of redundancy, and it belongs on the risk register with an owner and an end date, as any other change would.

RFor the users of cloud services, the London incident adds a second lesson: a design spread across zones still shared control-plane dependencies. Financial regulators were reported to be asking questions within a day3.

04/ 06
04 / 06OUR PERSPECTIVE

Date every chain, then test it whole

AKIS PLUS LTD's view is that every protective chain an owner relies on should carry a date: the last time it was made to work end to end, under realistic load, with the record kept. Component tests and maintenance logs matter, and they answer a smaller question. The board question is whether grid, batteries, generators, controllers and cooling worked together on a named day.

IGoogle's final report may find a specific defect in the London controllers. Whatever it finds, an owner that can show a recent whole-chain test is far better placed than one that can show only that two controllers were installed. This article draws no conclusion on the cause.

OUR PERSPECTIVE

Two controllers on the drawing are one asset if they fail the same way.

05/ 06
05 / 06QUESTIONS FOR THE BOARD

Three questions to ask this week

  1. For each protective chain we rely on, when was it last made to work end to end under load, and where is the record?
  2. Which of our duplicated controls share a design or a trigger that could make them fail together?
  3. What redundancy is out of service today for works, who owns that risk, and when does it return?
06/ 06
06 / 06WHAT TO WATCH

The next proof points

MilestoneWho decidesStatus
Google's final incident report for London, with preventative actions1Google CloudPromised, not yet posted on 26 October 2026
Actions from the July report, including the review of chiller pump control redundancy2Google CloudDates of August to October 2026 given in the report
Regulator and parliamentary inquiries into the London outage3FCA, PRA, Treasury CommitteeReported as open
BOTTOM LINE

A backup should be counted from the date it last worked end to end, and never from the date it was installed.

In London on 20 October 2026, both controllers meant to start the generators failed, and in July a backup unit and a cooling restart failed in the Netherlands. Owners should date every protective chain and test it whole.

EVIDENCE BOUNDARY

VVerified

  • The London incident of 20 October 2026: power interruption, UPS on load, primary and backup controllers failing to start the generators, batteries depleted, zone offline, as Google's Preliminary Incident Report states
  • The spread to unaffected zones through demand surges and control-plane dependencies, the 6 hours 10 minutes duration and the promise of a final report
  • The europe-west4-a incident of 15 July 2026: the 3 ms voltage drop, the side A backup unit failure, the row trip, the chiller controller, the redundant cooling source out for construction, 44°C and 14 hours 55 minutes, as Google's final report states
  • The actions and dates listed in the July report

RReported

  • The firms and services disrupted in London, and the actions of the FCA, PRA and Treasury Committee, as FinanceFeeds reports

AKPL analysis

  • A chain is as available as its least proved link
  • Duplicated controls that fail together behave as one asset
  • Planned works as a temporary loss of redundancy that belongs on the risk register
  • Dating every protective chain from its last end-to-end test, and the questions for the board

IInference

  • That an owner with a recent whole-chain test is better placed whatever Google's final report finds, which depends on a report not yet published
SOURCES AND EVIDENCE

Every source above is cited in the text by its number. Paragraphs marked A or I are KIS PLUS LTD analysis or inference.

CONNECT WITH KPL

Prove the backup before the grid does it for you.

Asset management and systems thinking for governments and the owners of critical infrastructure.

Start a conversation