Warnings that stayed on file
VAt about 17:30 on 13 August 2026 the northern wall of Compartment 1B at Samancor's Dikwena chrome mine near Brits collapsed, releasing nearly all the tailings stored there. The government reported no casualties and damage to the mine's infrastructure, a railway line and Eskom power lines3.
VIn a memorandum to Parliament dated 8 September 2026, the Chief Inspector of Mines, David Msiza, says a professional engineer's tailings report showed water seepage "from as far back as 2023", and that a further engineer's report before the collapse recorded seepage again in July 20261.
VUnder Regulation 23(4), paragraph c, of the Mine Health and Safety Act, seepage is a reportable dangerous occurrence, and the memorandum states that Samancor Chrome did not report it. The facility was also unregistered with the Department of Water and Sanitation, which Gazette 51657 of 29 November 2024 required1.
VA later written reply (question NW5107, dated 23 October 2026) records the department's findings: persistent seepage and prolonged saturation at the northern perimeter wall, inadequate monitoring and early warning, and recommendations in a structural-integrity report "requiring urgent engineering intervention" that were not implemented, including a continuous drainage system2. Neither document states a final cause.
The record was right and nothing followed it
AAn engineer's report is condition data with a recommended intervention. At Dikwena the condition record existed in 2023 and again in July 2026, and the regulator's account describes the missing link: no path from that record to a report, a registration or a repair.
VThe regulator also places accountability with the owner. Every notice goes to the employer, who "remains the accountable entity" although a third-party contractor operated the tailings facilities, and the notices apply equally to the contractor1.
Three lists a board can ask for
AThree lists would have shown the gap. The first holds the open engineering recommendations on every high-consequence structure, each with an age, an owner and a funded date. The second holds the observations that trigger a legal duty to report, with a record of whether each was reported. The third holds the assets run by contractors, where the duty to report is easily assumed to sit with someone else.
VThe department's position on the third list is plain: the Mine Health and Safety Act does not differentiate between a mine employee and a contractor employee1.
AA register of tailings and water-retaining structures can also be checked against the regulator's own registration requirement, which finds a missing registration before an inspector does.
Answer every recommendation with a date
AKIS PLUS LTD's view is that a recommendation from a competent engineer is a decision the owner has already been given, with only the date of the answer left open. An honest answer takes one of three forms: done, funded with a date, or declined by a named person who accepts the risk. A recommendation sitting in a file takes none of them, and in a regulator's later account it reads as a choice.
AThis differs from the closed recommendation of Issue 08, where the record shows work completed. At Dikwena, on the regulator's account, the record was right and the work was never started.
VThe Section 60 investigation is expected to take three months, and penalties or prosecution will be considered after it concludes1. The conclusions are the regulator's to draw.
OUR PERSPECTIVEAn engineer's warning on file is a decision the owner has already been given.
Three questions to ask this week
- Which engineering recommendations on our high-consequence assets are still open, how old is the oldest, and who owns each?
- Which observations in our inspection reports trigger a duty to report, and where is the record that each was reported?
- For every structure a contractor runs, who reports to the regulator, and where is that written down?