KIS PLUS LTD logo
KIS PLUS LTD
INNOVATECONNECTTRANSFORM
EXECUTIVE REAL-ESTATE INSIGHTNº 05
ASSET MANAGEMENTSYSTEMS THINKINGCRITICAL INFRASTRUCTURE
SELECTED FOR PUBLICATION · FRIDAY 2 OCTOBER 2026
GRID ACCESSDATA CENTRESLAND VALUE

The ten-year waitbelongs in the land price

Great British Grid promises faster connections, yet no connection date has moved. Developers are planning to wait a decade on gas, and the cost of that wait belongs in the price of the land.

BY KINGKOF OPOKU-OHEMENG3 MIN READFRI. 2 OCTOBER 2026
The wait in three numbers: the queue, the gap between opening date and connection date, and the proposed fee to hold a place.KPL GRAPHIC · DATA: OFGEM, BLOOMBERG, BUCKINGHAMSHIRE COUNCIL PLANNING RECORD
THE STRATEGIC SIGNAL

A grid reform widens who may build a connection. A site's value still follows the date its firm connection arrives, and no date has moved.

300 GW
of speculative capacity the government says it will remove from the connections queue
125 GW
of demand connection applications by June 2025, up from 41 GW in November 2024
10 years
the minimum wait ACRE Slough expects for a firm connection at Pinewood Nurseries
9 Oct
when public comments close on the Pinewood Nurseries application
01/ 06
01 / 06THE DEVELOPMENT

A public grid company arrives and the queue stays

COn 29 September, the government announced Great British Grid, a publicly owned body within Great British Energy, to work with NESO and Ofgem on connections reform and to remove more than 300 GW of speculative capacity from the queue1. Self-build connections and wider tendering of transmission are proposals, and the long-term budget is left to a future spending review1.

COfgem recorded demand connection applications rising from 41 GW in November 2024 to 125 GW by June 2025, with data centres accounting for most of it2. Its proposed remedy is a commitment fee of £237,500 to £712,500 per megawatt, refunded at energisation and forfeited on early exit, plus milestones for financial and commercial maturity2.

02/ 06
02 / 06THE KEY ISSUE

Developers are bridging the wait on site

RACRE Slough's roughly £570m data centre at Pinewood Nurseries would run on an on-site gas energy centre until a permanent connection arrives, which its application anticipates could take at least ten years3. Bloomberg also reported that Nscale's £2bn Loughton site, planned for 2027, may not have its 90 MW connection until the early to mid 2030s3. Nscale has explored fuel cells as interim power5.

RThe planning record shows an outline application for up to 40,500 square metres of data centre and a 5,000 square metre energy centre, received on 14 August, with comments closing on 9 October and a target decision of 4 December4.

03/ 06
03 / 06STRATEGIC ANALYSIS

Reform changes the queue, and the date stays with the site

RClearing speculative applications improves the odds for projects that remain, and self-build connections may shorten the wiring. Commentators observe that generation and network capacity stay open questions, and that how Great British Grid fits with Ofgem, NESO and the incumbents is yet to be set out6.

AFor value, the gap that matters sits between a site's opening date and its firm connection date. Gas covers that gap only if it wins planning and an environmental permit, satisfies nearby residents and keeps a purpose once the grid arrives. Each step costs time or money, and the cost lands on the owner, developer or lender, outside the price of land sold as powered.

FIGURE 01 · THE BRIDGING TEST
FIRM DATEA connection date in writing from the network. Prices the wait.
BRIDGE PERMITTEDPlanning and environmental consent in hand. Prices deliverability.
BRIDGE FUNDEDEquipment, fuel and running cost covered. Prices income.
AFTER THE BRIDGEA use for the engines once the grid arrives. Prices exit value.
AKPL framework. A site with an application and an assumption sits on the first rung; the price should say so.
04/ 06
04 / 06OUR PERSPECTIVE

Price the wait and name who carries it

ALenders and buyers should ask for the connection date in writing and value the bridge as a project of its own. Sites with a firm date, a consented bridge and a plan for the engines afterwards earn a premium. Sites with an application and an assumption earn a discount that grows with every year of wait. Demand follows for independent bridge reviews, permit tracking and valuations that model decommissioning.

OUR PERSPECTIVE

Reform moves the queue. The site still owns its wait.

05/ 06
05 / 06RISKS AND REGULATION

What would prove this wrong

IIf Great British Grid and Ofgem's milestones release firm connection dates well inside a decade, bridges shrink to short stopgaps and the discount fades. If planning authorities refuse gas-led schemes, land bought for its grid claim is stranded. The Pinewood decision, targeted for 4 December, is an early test of both4.

06/ 06
06 / 06WHAT TO WATCH

The proof points

MilestoneWho decidesStatus
Public comments close on the Pinewood Nurseries application4Buckinghamshire Council9 Oct 2026
Target decision on the Pinewood Nurseries application4Buckinghamshire Council4 Dec 2026
Ofgem decision on the commitment fee and queue milestones2OfgemDate not set; consultation closed 16 Sep
Scope, legislation and budget for Great British Grid1Government, Great British EnergySpending review; no date set
BOTTOM LINE

Value follows the date power arrives, and no reform has yet supplied a date.

Until a network states a connection date in writing, a data-centre site holds a hope. Price that hope at the cost of waiting: the bridge, its consents and what it leaves behind.

EVIDENCE BOUNDARY

CConfirmed

  • Great British Grid, the 300 GW queue pledge, and self-build connections as a proposal
  • Ofgem's queue figures (41 GW to 125 GW) and its proposed commitment fee and milestones

RReported

  • ACRE Slough's ten-year assumption and gas bridging (Bloomberg)
  • Nscale Loughton's connection timing and interim fuel cells (Bloomberg, Data Centre Review)
  • The Pinewood application dates, floorspace and target decision (an aggregation of the Buckinghamshire Council record)
  • Commentary that self-build addresses the wiring, with generation and network capacity still open (Resultsense)

AKPL analysis

  • The gap between opening date and firm connection date as a valuation test
  • The bridging test

IInference

  • That firm dates arriving early would shrink the discount, and that refusals would strand land bought for its grid claim. Both depend on events not yet happened.
SOURCES AND EVIDENCE

Every source above is cited in the text by its number. Paragraphs marked A or I are KIS PLUS LTD analysis or inference.

CONNECT WITH KPL

Ask for the connection date before you price the land.

Asset management and systems thinking for governments and the owners of critical infrastructure.

Start a conversation