SELECTED FOR PUBLICATION · WEDNESDAY 11 NOVEMBER 2026
SYSTEMS ENGINEERINGSYSTEM DYNAMICSASSET MANAGEMENT

Restored, still fragile.La Palma's power was back by 10:26 on 2 November, and two days later the same plant dropped out again

On 2 November 2026 the Canary island of La Palma lost all 50,508 of its electricity supplies when every thermal unit at its main plant disconnected during a storm. Full supply was confirmed at 10:26, and on 4 November several units at the same plant dropped out again. The causes are under investigation. The question for every owner is when a restored system has its margin back.

BY KINGKOF OPOKU-OHEMENG6 MIN READWED. 11 NOVEMBER 2026
KPL system map, drawn from the operators' and the Canary Islands government's accounts as reported in the sources cited in this issue, and from the ministry's tender. Schematic, not to scale.KPL GRAPHIC · DATA: ENDESA, RED ELÉCTRICA AND THE CANARY ISLANDS GOVERNMENT AS REPORTED BY DIARIO DE AVISOS, DIARIO PALMERO AND HÍBRIDOS Y ELÉCTRICOS; MITECO
KPL SYSTEM REPLAY · SCHEMATIC, NOT TO SCALE
THE STRATEGIC SIGNAL

A system whose supply is back still carries its old exposure until its margin is back, so recovery should be counted from the moment it can survive the next event.

50,508
supplies lost at 06:38 on 2 November, the whole island
1
66 kV line between the main plant and the west of the island
22 min
second cut on 4 November, 13,740 supply points
52 MW
firm capacity tendered for La Palma, for needs forecast for 2031
01/ 06
01 / 06THE REAL PROBLEM

Two failures in three days on one island grid

RAt 04:10 on Monday 2 November 2026, during heavy rain and storms, a fault on the 66 kV Guinchos-Valle transmission line cut supply at the Valle substation and left 17,624 customers on La Palma without power. By 05:40 they were back through switching on the medium-voltage network, with the high-voltage line still out of service.1

RAt 06:38 the island went to what Spain calls a cero energético, a total blackout of all 50,508 supplies. Red Eléctrica confirmed that every thermal generation group had disconnected, and said it had not identified what triggered the simultaneous disconnection; a link to the storm is possible and unconfirmed.12

RRestoration began at 07:56. One mobile gas unit had difficulty starting, so a diesel unit was brought in and connected at 08:40; about 1,300 customers were back around 09:00, and Endesa and Red Eléctrica confirmed full supply at 10:26.12

RTwo days later, at 07:23 on Wednesday 4 November, several generation groups at the Los Guinchos plant disconnected again and 13,740 supply points lost power for 22 minutes. Endesa said it did not yet know the cause.4

AThe visible problem is a stormy night and an unexplained trip. The system problem is margin. The island was running with so little that one line fault and one plant event were enough to take every customer, and Monday's restoration returned the supply while leaving the margin where it was.

02/ 06
02 / 06FIVE DIAGNOSTIC SIGNALS

What a grid with no spare path looks like

ROne line between the plant and the west. A single 66 kV line links Los Guinchos, in the east of the island, with the Valle de Aridane substation in the west, and some distribution areas are radial, with no alternative supply path if a section fails.3

RNo neighbour to lean on. La Palma is an isolated electrical system with no connection to the mainland grid, so it cannot import emergency power when its own generation fails.3

REvery unit out together. Red Eléctrica confirmed that all the thermal generation groups disconnected at 06:38, so one event removed the whole island's conventional supply at once.2

RA restart that depends on old machines. Some units had difficulty starting during restoration, and Endesa says several Los Guinchos groups are between 50 and 54 years old.24

RA repeat that follows a pattern. In June 2025 the Canary Islands energy minister said the plant's most powerful gas unit failed and the three other units in service could not take the load, leaving more than 50,000 people without power. On 3 October 2026 Lanzarote went to zero when a second fault struck during the switching to restore it.67

03/ 06
03 / 06THE COMPLEX SYSTEM

One plant, one line and a replacement calendar

AThe island's supply joins assets, operations, finance and policy: one main plant, one transmission circuit, a partly radial network, the operators who restore it, and a renewal set by national tender and permits. Three disciplines ask distinct questions of it.

AThe requirements question (systems engineering): what single event must the island survive without losing every supply, and what evidence shows it can? The time question (system dynamics): after a restoration, how long until the system can again ride through the same event, and what is it exposed to in between? The condition question (asset management): how reliable are units past 50 years of service, and how is that risk carried until their replacements arrive?

VThe Ministry for the Ecological Transition launched its second firm-capacity tender for Spain's non-peninsular systems on 14 July 2026. It aims to cover supply needs forecast for 2031, includes 52 MW for La Palma, and penalises Canary Islands groups that will be more than 40 years old in 2031.5

ROn the network, a new substation at Las Breñas and a second 66 kV line to Valle de Aridane have been proposed. Red Eléctrica began processing the project in 2024, and it still needs its procedures and authorisations.3

IUntil both arrive, the island's resilience after any restoration rests on the same units and the same single line that were in place before the failure, so the time it takes to rebuild margin is set by procurement and permitting calendars measured in years.

AKPL calls this restored margin: the reserve a system has regained after a restoration, measured by its ability to ride through the next event, whatever the time at which supply came back.

FIGURE 01 · FROM ONE LINE TRIP TO A SECOND CUT
LINE TRIPS04:10, 17,624 off
SWITCHED05:40, line still out
ISLAND AT ZERO06:38, 50,508
FULL SUPPLY10:26, same units
CUT AGAIN4 Nov, 22 minutes
RThe sequence as reported from the operators' and the regional government's accounts. The causes are under investigation.
04/ 06
04 / 06KPL DECISION FRAMEWORK

Count recovery from the day the margin is back

ADeclare the margin state after every restoration. Report whether the system can again survive the event that took it down, as a separate figure from the time supply returned.14

AFind the events that take everything. Identify each single line, plant or protection setting whose loss removes all supply, and test the restoration path that follows it.23

AProve the restart on the machines you have. Test the units a restart depends on under realistic conditions, and plan for one of them failing to start.1

ARun the old fleet as a managed risk. While replacements wait on a tender, set condition monitoring, spares and operating limits for the oldest units, with a named owner.45

AJoin the calendars. Put generation tenders, network permits and the risk carried in between on one programme that the ministry, the network operator and the generator all see.35

OUR PERSPECTIVE

Supply came back at 10:26. The margin waits on the tender calendar.

05/ 06
05 / 06QUESTIONS FOR THE BOARD

Six questions for any owner of an isolated or weakly connected system

AThe same pattern runs through remote mines, airports and data centres on a single feed: wherever one asset carries the whole load and its replacement runs on someone else's calendar.

  1. After our last major restoration, how long was it before we could survive the same event again, and who measured it?
  2. Which single asset or setting, if lost, takes every customer with it?
  3. When did we last start our restart units under realistic conditions, and what happens if one fails?
  4. What operating limits and monitoring apply to our oldest units while their replacements wait?
  5. Who owns the risk between a replacement being decided and it entering service?
  6. Do our generation, network and permitting calendars sit on one programme?
06/ 06
06 / 06WHAT WE ARE WATCHING

The dates that will confirm or overturn the analysis

AFollow-through on Nº 13 and Nº 10: KPL searches on 10 November found no report of the Barking line reopening and no NATS full investigation report; both remain open.

AKPL will return to this story when the operators publish the cause of the 2 November disconnection, or when La Palma's tendered capacity is awarded.

MilestoneWho decidesStatus
Cause of the simultaneous disconnection at 06:38 on 2 November2Red Eléctrica, Endesa and the Canary Islands governmentUnder investigation
Cause of the 4 November cut4EndesaUnknown at 4 Nov
Las Breñas substation and second 66 kV line3Red Eléctrica and the authoritiesAuthorisations pending
Award of La Palma's 52 MW in the second firm-capacity tender5MITECOLaunched 14 Jul 2026
Any further island-wide zero14Endesa and Red EléctricaTwo events in three days
BOTTOM LINE

The lights came back at 10:26. The margin is still on order.

La Palma's supply returned within hours on 2 November, with the same single line and the same ageing units in place, and two days later part of the island went dark again. Owners who count recovery from the moment their system can survive the next event, and who join the replacement calendar to the risk carried in between, will see their real exposure.

EVIDENCE BOUNDARY

VVerified

  • The ministry's second firm-capacity tender for the non-peninsular systems: launched 14 July 2026, needs forecast for 2031, 52 MW for La Palma, a penalty for Canary Islands groups more than 40 years old in 20315

RReported

  • The timeline of 2 November: the line trip at 04:10 and 17,624 customers, the restoration at 05:40, the zero at 06:38 and 50,508 supplies, restoration from 07:56, the mobile gas unit and the diesel unit at 08:40, about 1,300 customers at about 09:00, full supply at 10:261
  • Red Eléctrica's confirmation that all thermal groups disconnected, its open investigation, the starting difficulties and the unconfirmed link to the storm2
  • The single 66 kV line, the radial distribution areas, the isolated system and the proposed Las Breñas substation and second line3
  • The cut of 4 November: 07:23, 13,740 supply points, 22 minutes, cause unknown to Endesa, and Endesa's account of groups between 50 and 54 years old4
  • The June 2025 blackout as described by the Canary Islands energy minister6
  • The Lanzarote zero of 3 October 2026 and the second fault during restoration switching7

AKPL analysis

  • The reading of the events as a restoration that returned supply without returning margin
  • The three questions, the concept of restored margin and the five decision principles
  • The six board questions, and the follow-through on Nº 13 and Nº 10

IInference

  • That until the new capacity and the second line arrive, the time to rebuild margin is set by procurement and permitting calendars measured in years
SOURCES AND EVIDENCE
01Diario de AvisosLa Palma recupera el 100% del suministro eléctrico tras casi cuatro horas de apagón generalRegional press, reporting the Cabildo, Endesa and Red Eléctrica via EFE2 November 2026
04Diario de AvisosSegundo apagón en dos días en La Palma: la eléctrica señala a las administracionesRegional press, reporting Endesa4 November 2026
05Ministry for the Ecological Transition (MITECO)El MITECO lanza un nuevo concurso de potencia firme en los territorios no peninsularesGovernment announcement14 July 2026
06Diario de AvisosEl apagón de luz de La Palma: ¿es una advertencia para el resto de Canarias?Regional press, reporting the Canary Islands government12 June 2025
07Diario de AvisosCero energético en LanzaroteRegional press3 October 2026

The primary source is the Ministry for the Ecological Transition's own announcement of its second firm-capacity tender. Every operational fact rests on press reports of the operators' and the Canary Islands government's accounts: Diario de Avisos carries the Cabildo's timeline and Red Eléctrica's sources via EFE, and Diario Palmero carries Red Eléctrica's confirmation. Red Eléctrica's own press note was searched for and not found. The unit ages are Endesa's as reported. The causes of both events of November 2026 are under investigation, and reports differ on the trigger; this article draws no conclusion on cause or responsibility. Paragraphs marked A or I are KIS PLUS LTD analysis or inference and are not attributed to any source.

CONNECT WITH KPL

Know when your system has its margin back.

Asset management and systems thinking for owners of isolated and weakly connected systems, from finding the single events that take every customer to proving restart and carrying ageing assets safely until their replacements arrive.

Start a conversation

© 2026 KIS PLUS LTD. Quote up to two sentences with credit and a link to this page. To republish or reproduce more, ask us.