Two failures in three days on one island grid
RAt 04:10 on Monday 2 November 2026, during heavy rain and storms, a fault on the 66 kV Guinchos-Valle transmission line cut supply at the Valle substation and left 17,624 customers on La Palma without power. By 05:40 they were back through switching on the medium-voltage network, with the high-voltage line still out of service.1
RAt 06:38 the island went to what Spain calls a cero energético, a total blackout of all 50,508 supplies. Red Eléctrica confirmed that every thermal generation group had disconnected, and said it had not identified what triggered the simultaneous disconnection; a link to the storm is possible and unconfirmed.12
RRestoration began at 07:56. One mobile gas unit had difficulty starting, so a diesel unit was brought in and connected at 08:40; about 1,300 customers were back around 09:00, and Endesa and Red Eléctrica confirmed full supply at 10:26.12
RTwo days later, at 07:23 on Wednesday 4 November, several generation groups at the Los Guinchos plant disconnected again and 13,740 supply points lost power for 22 minutes. Endesa said it did not yet know the cause.4
AThe visible problem is a stormy night and an unexplained trip. The system problem is margin. The island was running with so little that one line fault and one plant event were enough to take every customer, and Monday's restoration returned the supply while leaving the margin where it was.
What a grid with no spare path looks like
ROne line between the plant and the west. A single 66 kV line links Los Guinchos, in the east of the island, with the Valle de Aridane substation in the west, and some distribution areas are radial, with no alternative supply path if a section fails.3
RNo neighbour to lean on. La Palma is an isolated electrical system with no connection to the mainland grid, so it cannot import emergency power when its own generation fails.3
REvery unit out together. Red Eléctrica confirmed that all the thermal generation groups disconnected at 06:38, so one event removed the whole island's conventional supply at once.2
RA restart that depends on old machines. Some units had difficulty starting during restoration, and Endesa says several Los Guinchos groups are between 50 and 54 years old.24
RA repeat that follows a pattern. In June 2025 the Canary Islands energy minister said the plant's most powerful gas unit failed and the three other units in service could not take the load, leaving more than 50,000 people without power. On 3 October 2026 Lanzarote went to zero when a second fault struck during the switching to restore it.67
One plant, one line and a replacement calendar
AThe island's supply joins assets, operations, finance and policy: one main plant, one transmission circuit, a partly radial network, the operators who restore it, and a renewal set by national tender and permits. Three disciplines ask distinct questions of it.
AThe requirements question (systems engineering): what single event must the island survive without losing every supply, and what evidence shows it can? The time question (system dynamics): after a restoration, how long until the system can again ride through the same event, and what is it exposed to in between? The condition question (asset management): how reliable are units past 50 years of service, and how is that risk carried until their replacements arrive?
VThe Ministry for the Ecological Transition launched its second firm-capacity tender for Spain's non-peninsular systems on 14 July 2026. It aims to cover supply needs forecast for 2031, includes 52 MW for La Palma, and penalises Canary Islands groups that will be more than 40 years old in 2031.5
ROn the network, a new substation at Las Breñas and a second 66 kV line to Valle de Aridane have been proposed. Red Eléctrica began processing the project in 2024, and it still needs its procedures and authorisations.3
IUntil both arrive, the island's resilience after any restoration rests on the same units and the same single line that were in place before the failure, so the time it takes to rebuild margin is set by procurement and permitting calendars measured in years.
AKPL calls this restored margin: the reserve a system has regained after a restoration, measured by its ability to ride through the next event, whatever the time at which supply came back.
Count recovery from the day the margin is back
ADeclare the margin state after every restoration. Report whether the system can again survive the event that took it down, as a separate figure from the time supply returned.14
AFind the events that take everything. Identify each single line, plant or protection setting whose loss removes all supply, and test the restoration path that follows it.23
AProve the restart on the machines you have. Test the units a restart depends on under realistic conditions, and plan for one of them failing to start.1
ARun the old fleet as a managed risk. While replacements wait on a tender, set condition monitoring, spares and operating limits for the oldest units, with a named owner.45
AJoin the calendars. Put generation tenders, network permits and the risk carried in between on one programme that the ministry, the network operator and the generator all see.35
OUR PERSPECTIVESupply came back at 10:26. The margin waits on the tender calendar.
Six questions for any owner of an isolated or weakly connected system
AThe same pattern runs through remote mines, airports and data centres on a single feed: wherever one asset carries the whole load and its replacement runs on someone else's calendar.
- After our last major restoration, how long was it before we could survive the same event again, and who measured it?
- Which single asset or setting, if lost, takes every customer with it?
- When did we last start our restart units under realistic conditions, and what happens if one fails?
- What operating limits and monitoring apply to our oldest units while their replacements wait?
- Who owns the risk between a replacement being decided and it entering service?
- Do our generation, network and permitting calendars sit on one programme?
The dates that will confirm or overturn the analysis
AFollow-through on Nº 13 and Nº 10: KPL searches on 10 November found no report of the Barking line reopening and no NATS full investigation report; both remain open.
AKPL will return to this story when the operators publish the cause of the 2 November disconnection, or when La Palma's tendered capacity is awarded.